7:15am- Digging is back underway this morning as crew will work until rains hit...
8:30am- 1st joint in and grading rock for #2.
9:20am- 3rd joint of the day. Light rain falling at this time.
10:30am- 4th joint going in.
11:10am- Joint #5 going in.
1:20pm- 6th joint in place as crew prepares to set MH A4.
2:30pm- MH A4 base now set and tied to line with a 6.5’ piece of pipe.
3:45pm- barrel section on A4 and is getting wrapped and strapped. Alignment to MH A5 is done as excavator begins digging out for next joint of pipe for today.
4:30pm- a joint is now laid upstream of MH A4. Crew will continue to gravel And then backfill over line to finish out the day.