7:00am- Pump not running this morning. Crew will fuel pump and begin pumping water to start the day.
8:38am- crew has set another pump at A3 so that laser could be placed in A5 manhole. Dug out now and preparing to set 1st joint of the day.
8:53am- Testing on line and manholes begins again today...Vacuum test on A23 will start things.
9:13am- MH A23 passes vacuum test.
-Pipe crew going home due to equipment break down. No pipe is laid today.
10:06am- MH A22 passes vacuum test.
10:06am- MH A22 passes vacuum test.
11:00am- MH A21 passes vacuum test.
12:23pm- MH A20 passes vacuum test. Some equipment issues occurred.
1:15pm- MH A19 passes vacuum test.
1:54pm- MH A18 passes vacuum test.
2:33pm- MH A17 passes vacuum test.
4:06pm- MH A15 passes vacuum test.