6:50am- Pipe crew will continue with laying pipe today. More line testing will also occur. 

7:45am- testing crew is now setting up a vacuum test at MH A14. 

8:06am- MH A14 passes vacuum test. 

8:48am- MH A13 passes vacuum test. 

9:37am- Line test now started on MH A12-A13. 
466.18’@2 hours and 15 minutes. 

10:15am- 2nd joint for today so far. 

11:38am- #5 is now in place. 

11:50am- Line from MH A12-A13 passes air test. 

1:23pm- line on test now from A11-A12 manholes. 
169’@49 minutes. 

2:14pm- Line A11-A12 passes air test. 

3:16pm- MH A12 passes vacuum test. 

3:57pm- MH A11 passes vacuum test. 

4:30pm- Joint #12 going in now for the pipe crew today. 

5:00pm- #13 getting placed. Backfill will round out the day. 