6:50am- Pipe crew will continue with laying pipe today. More line testing will also occur.
7:45am- testing crew is now setting up a vacuum test at MH A14.
8:06am- MH A14 passes vacuum test.
8:48am- MH A13 passes vacuum test.
9:37am- Line test now started on MH A12-A13.
466.18’@2 hours and 15 minutes.
10:15am- 2nd joint for today so far.
11:38am- #5 is now in place.
11:50am- Line from MH A12-A13 passes air test.
1:23pm- line on test now from A11-A12 manholes.
169’@49 minutes.
2:14pm- Line A11-A12 passes air test.
3:16pm- MH A12 passes vacuum test.
3:57pm- MH A11 passes vacuum test.
4:30pm- Joint #12 going in now for the pipe crew today.
5:00pm- #13 getting placed. Backfill will round out the day.