Turkey Creek Ph 1 - Flat Creek (Line Work)


-It will be a late start today due to Voting.
8:45am- gravel now going in for grading of 2nd joint for the day. 

9:35am- 3rd joint getting graveled up. 

11:20am- after some rick breaking and equipment difficulties, the 4th joint goes in. 

1:00pm- 5th joint for today. 

2:40pm- 6th joint in place as hammer goes back on to break more rock. 

3:35pm- 7th joint now in place. 

4:50pm- 8th and final joint for today going in. More gravel and backfill to finish out the day. 