6:55am- testing crew setting up line test from MH A9 to A8.
7:05am- Pipe crew will continue with laying of pipe and will also start encasement today at STA 19+50 for the 20’ per plans.
8:30am- crew having issues with the test ball agin today. Some fittings appear to be cracked. They are in the process of getting them replaced.
8:55am- pipe crew putting 1st joint of the day in. They moved the water pumps around first thing this morning.
9:26am- more dirt is moved around near stream bank stabilization and bend way weirs.
9:44am- 2nd joint being placed.
10:26am- 3rd joint now.
1:24pm- Line is now finally under test from MH A8- A9. 272’@ 1hour and 18 minutes.
2:11pm- joints 4&5 now placed with rebar set for encasement that is scheduled to be poured at 3pm today.
2:37pm- Line from MH A8-9 passes air test.
2:54pm- MH A8 passed vacuum test.
3:20pm- encasement now finished @ STA 19+50. Backfill with gravel now.
4:08pm- 6th joint now placed.
4:26pm- backfill will consume the rest of the day.