Thursday, November 19, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


12:00pm- crew is nearing MH A6 location. Good chance Manhole will be set today. 

1:34pm- joint 5 is laid and area dug on out to bore pipe. Gravel and grading for MH A6 next. 

2:11pm- grading out gravel for MH A6. 

3:00pm- taking measurements for pipe to meet manhole. 

4:30pm- manhole A6 base is now set and tied to bore pipe. 

4:45pm- gravel being placed. 

5:00pm- backfill begins. Crew will call it a day here shortly. 