Turkey Creek Ph 1 - Flat Creek (Line Work)


7:05am- Crew will be pumping water in order to finish stacking out MH A6 today.

9:04am- grading today on 12” line area on access roadway at power substation. 

10:15am- substation area now graded and access road too is also being graded. 



11:34am- wrapping and strapping of manholes will pick back up today at MH A4.

12:56pm- boot now going on bore casing and pipe here at A6 location. 

2:22pm- moving of spoils begins today. Crew to level up low spot between MH A3-A4.

3:25pm- MH A5-A6 is now lamped by daylight. 861’. 

3:43pm- gravel going in at boot now so that pipe can be backfilled. 

4:30pm- more spoil moving continues and will round out the day. 