6:50am- Pipe crew will try and lay again today if equipment stays running. Excavator was worked on yesterday by a mechanic.
7:23am- 1st joint for today going in. Crew will continue with laying pipe and I will be going over to be with line testing crew and stop back in on pipe crew periodically.
8:36am- 2nd joint going in.
9:45am- 3rd joint now getting placed.
11:10am- A vacuum test on MH A16 now passes test. Testing crew will move equipment now to do a line test and more vacuum testing.
1:16pm- A line test has begun on MH A14-A15. 199’@58 minutes.
2:13pm- Line from MH A14-15 passes air test.
3:05pm- Line test underway on MH A13-A14. 337’@98minutes.
4:56pm- Line from A13-14 passes air test.
Pipe crew has laid their 7th joint for the day.