Wednesday, November 4, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


Crew back to lat more pipe today, but first fuel filters are getting changed on excavator. 
7:55am- getting laser set back up this morning. 

8:25am- 1st  joint for today now placed. 

9:20am- 2nd joint going in after some rock breaking that occurred. 

10:32am- 3rd joint now placed. 

11:17am- 4th joint now laid. 

12:40pm- 5th pipe laid for today as MH A5 will be going in next. 

2:15pm- MH A5 base is set and a 5’ piece ties it to the line. 

MH A5 to A4 is lamped by laser. 

3:35pm- MH A5 now has barrel sections added and alignment to MH A6 is underway. 

4:55pm- crew has laid the first joint upstream of MH A5 and are in the process of wrapping and strapping the sections. 

Backfill will round out their day. 