6:55am- not as much water this morning as was being anticipated. Currently pumping water from MH A3 area, but crew will set another pump here before they start laying pipe here at approximately STA 19+00.
7:47am- line from MH A10-11 is now under test. 495’ @ 2hours and 23 minutes.
9:14am- line testing crew is now in the process of mending some fences here on Laytons property near MH’s A12-14.
10:16am- Line passes air test from MH A10-11.
11:09am- 2nd joint of pipe so far today. Rock breaking occurring on and off.
1:34pm- Line now on test from MH A9 - A10. 377.5’@ 1hour and 50 minutes.
1:42pm- 4th joint for today...
3:25pm- Line from MH A9-10 passes line test.
3:44pm- MH A9 passes vacuum test.
4:50pm- pipe crew has laid 7 joints of pipe for the day.