6:55am- crew will be laying pipe again today from MH A5 area upstream.
8:25am- pumps are swapped out due to one not running right.
A lot of water coming into ditch at this time.
9:25am- 1 joint laid so far as crew battles water running into ditch.
11:15am- 3rd joint for today now placed. Some rock breaking occurred on this piece.
1:40pm- 4th joint getting gravel.
2:48pm- 5th joint now placed.
4:55pm- 7 joints laid for today. Crew will gravel up pipe rest of the way and backfill.