Monday, November 2, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:10am- Its looking like the crew will be able to lay pipe again finally. Currently one joint upstream of MH A4.

7:52am-1st joint of the day going in. 

8:52am- 2nd joint in and digging on next one. 

9:30am- 3rd bow in place. 

10:20am- 5th joint now placed. 

11:45am- 7th joint being placed. 

1:10pm- 8th joint getting gravel.

2:13pm- 9th joint placed and hammer is getting hooked up for rock breaking. 

3:05pm- joint #10 getting gravel. 

3:55pm- breaking rock now for 11th joint to be installed. 

4:42pm- 11th and final joint for today going in. Backfill will use up rest of the day. 









 