6:50am- Testing crew is setting up a line test from MH A7-A8 this morning. Pipe crew will continue with laying pipe from roughly STA 19+ 70 upstream.
7:37am- Line now on test from MH A7-8. 873’@4 hours and 13 minutes.
7:54am- more fence work on Layton today at RR03 bore pit area while test is going.
8:16am- 1st joint going in for today so far.
9:21am- 2nd joint now laid.
10:11am- 3rd now getting placed.
11:38am- 4th joint getting gravel.
11:50am- Line passes air test from MH A7-8.
12:39pm- MH A7 passes vacuum test.
1:43pm- 5 joints are in as excavator now moves spoil pile from bore pit so that they can continue to dig.
3:07pm- #6 & #7 now placed.
3:52pm- 8th joint now being laid.
Crew will also be moving pump now to MH A6 area to begin pumping water from it and continue moving spoil pile for needed room to work.
5:16pm- water is now mostly out of MH A6 area.