Thursday, December 5, 2019

Turkey Creek Phase 1


2:00pm- R.L. Persons has dug down today where the Liftstation will set to see about rock. Rock was encountered at about 13 feet. 

Site was also cleared from Fence of WETD to STA 1+42. 

3:10pm- Lift Station  crew is benching down some
and moving material around. 

3:50pm- Flat Creek crew has cut topsoil today and installed rock at Mr. Heads property and out at staging area for materials on Mr. Rittenhouse property. 

Area now cleared from STA 5+50 back to MH A3 Bore pit location. Brush and trees are mostly burnt up at this time. 

Property owners as mentioned above were onsite today. I met with Brad and we spoke with them about the project and they seemed to be understanding and cooperative. Contractor for the pipe work is working with the land owners and doing what they can to accommodate them currently. 
5:25 pm- I will now be headed offsite. 