Crew will work at the Access Road 3 entrance today installing gate posts and getting the fence put back up.
12:30pm- Back onsite from Inspecting manholes that have been repaired in Branson Creek.
Crew now has fence posts set at roadway where entrance radius will begin.
1:20pm- I’m having the 0-6” rock cut and moved to match center of where gate should be.
2:55pm- concrete going in around steel gate posts now.
4:30pm- Posts are now set in place for the gate here on access road 3.
5:10pm- I will now be headed offsite.