Wednesday, December 18, 2019

Turkey Creek Ph1 - Flat Creek (Line Work)


Crew will finish building fence on access road 3; burn brush pile at entrance; continue to strip topsoil in the bottom area. 

8:14am- Fence work is underway. 

9:25am- Entrance fencing at gate on access road 3 now finished. 

9:30am- Brush pile now started on fire. 

11:00am- Staging area getting 0-6” rock today as topsoil is pushed up. 

2:40pm- Brush piles in the bottom area of access 3 are now lit on fire. 

2:50pm- North end area of the easement has tree logged now and stacked up, while another brush pile is trying to burn. 


5:00pm- crew will be tracking equipment back up to top tonight. Excavator to begin clearing near power substation from A36 thru A28MH’s. 