Tuesday, December 3, 2019

Turkey Creek Phase 1


Spoke with R.L. Persons (Contract 1) today and Mike has stated that the equipment will begin showing up at the WWTF tomorrow. 
1:40pm- Flat Creek (Contract 2) has begun road work on access road 1 and clearing of R.O.W. from STA 3+68 (MH A3) to STA 5+50 approximately. 
Access road 1 at beginning. 
As you start down hill to Mr. Heads property. 

Dirt here to be removed and replaced with rock. 

2:00pm- At tree line coming into field to Line A area. 

Looking back up to tree line from point south of bore pit near STA 21+63. 

Looking North towards STA 6+00

Looking back South from STA 6+00 to STA 21+63. 

2:05pm- Looking North into clearing from STA 5+50.

2:35pm- Looking South from Bore Pit at MH A3. 

4:25pm- Looking North to MHA3. 

5:05pm- From MHA3 area looking back south. 

5:15pm- Some large piles have been pushed up. One to burn on the right, and the other to keep for cedar logs per property owners request. 

5:30pm- end of the day. 