Tuesday, December 10, 2019

Turkey Creek Ph 1 - Flat Creek (Line work)


7:30am- crew preparing to move equipment to access road 3 today. 

8:15am- Equipment is now at Access road 3 to begin work. Excavator will be next. 

8:50am- Loading the excavator created a couple issue with the edge of the roadway that will have to be fixed at some point. 



9:20am- Excavator now at access road 3. Crew will be just a bit before getting started grading roadway. 

11:00am- Dozer now working to clear an area for staging materials at the entrance of access road 3. Property owner is allowing for this area to be built.  

1:00pm- I have spoken with Mr. Rittenhouse and he and I will drive access road 3 tomorrow morning and flag anything that is important to him to ensure nothing gets disturbed. 
Staging area prepped now. No rock will be placed here until it’s needed. 

3:10pm- Dozer and Excavator have now worked their way down Access road 3 to a point not half way yet. Still prior to monument location. 



4:30pm- Excavator has now made it about 100yds past monument area. Dozer to follow on up behind it. Roadway is very drivable now with what has been done with very minimal clearing of cedar trees that have overhang the roadway. 

4:45pm- now headed offsite to WWTF for final check of the day. 