Friday, December 27, 2019

Turkey Creek Ph1 - Flat Creek (Line Work)


Excavator is tracking in on Access Road 3 to begin clearing across the creek towards substation. Drilling crew will pick back up at substation and continue drilling today with possible blasting to occur. 
7:25am- Drilling crew preparing machine this morning. I have confirmed that blasting will take place today before noon if everything thing goes as planned. 

9:25am- Drill crew is now up on the flat area in front of substation. 

10:45am- Blasting materials should arrive in the next hour as the crew continues to drill. 

11:30am- Excavator now preparing to cross the creek once these last few trees are removed. 



12:35pm- The first blast of the project is shot at this time. 





2:12pm- Second blast occurs. No more drilling or blasting today. 

Skid steer cleans up rock for access to substation. 

3:00pm- Excavator now across creek with another brush pile getting established. 

5:00pm- All Gates are locked for the weekend. I’ll now be headed offsite. 