Crew onsite. Base rock will be placed on the hill at Mr. Heads property, then crew will cut top soil off on access road 3 where it enters into the field area.
10:15am- Rock is now arriving for access road 1 from Mr.Heads property to the gate for a few areas that need touch up work.
10:40am- rock placed in a few spots now. Dozer to be hauled to access road 3 now.
11:30am- Dirt is pushed from easement today to stock pile it along A20 MH area.
1:00pm- Ground Breaking Ceremony at the WWTF.
3:00pm- Job Board now up at Access road 3 Entrance.
Also at this time two additional posts have been set the were provided by the property owner to go between gate posts and main fence.
3:35pm- Topsoil still getting cut back in easement.
5:30pm- Gate for Access Road 3 now up.