Crew begins their day setting large brush pile on fire below substation this AM.
7:30am- Fire starting to burn now.
7:50am- Drilling crew onsite to begin drilling holes today. Blasting scheduled for tomorrow depending on how today goes.
11:00am- Two loads of 12” SDR35 & SDR21 pipe have arrived today. Crew will begin unloading and placing it out of the way.
12:10am- 2nd truck is getting unloaded at the substation site.
12:30pm- Drilling begins near STA 115+25.
2:35pm- Drilling has now reached STA 116+40 approximately.
4:40pm- Drilling crew has made it just about to the top of the hill now. Maybe 20’ to go. A blast should be set off sometime before noon tomorrow.
Fires are burning up nicely at this time.
5:00pm- Gates are now locked up and equipment has been moved back to access road 3 so that clearing across the creek can begin tomorrow.