Tuesday, December 31, 2019

Turkey Creek Ph 1 - Flat Creek (Line Work)


It appears that not only drilling, but Blasting also occurred yesterday afternoon. It looks as though it went ok. 

Drilling crew will not be onsite today. 

8:00am- Brush piles are lit on fire this morning as clearing continues between the creek and the tunnel at the railroad tracks. 

9:10am- More piles of brush are set on fire. 

Last turn at MH 26 to Railroad tunnel. 

10:00am- Survey is onsite doing level loops today again.

11:20am- Another large debris pile is formed. 

12:50pm- With the Railroad’s tracks in site, not much more clearing left now. 

1:00pm- Logs are brought over to Access road 3 side of the creek. Fire is creeping out into the grass at the burn pile on this side as crew begins putting it out. 



Since only more clearing is to be done, I will now be headed offsite for rest of today. 