Monday, December 9, 2019

Turkey Creek Ph 1 - Flat Creek (Line Work)


8:50am- Entrance for access road 3 is getting built today. 

9:35am- More roadway is dug out for 0-6” rock at Mr. Heads Property on access road 1. 

10:10am- Access road 3 entrance now rocked in place. 

11:45am- More clearing of brush along access road 1 on Rittenhouse is getting done per property owners request and agreement with Flat Creek. 

12:10pm- Another load of 0-6” rock going down at Mr. Heads property crossing. 

12:30pm- crossing completed. 

12:40pm- Staging area back on Rittenhouse property is now covered with 0-6” rock along with rest of roadway into bottom field. 



2:40pm- A small diameter drain line will now be installed across access road 1 at the spring area to help with keeping the water out of the roadway. 

2:50pm- Pipe is now across access road 1 at the spring. 

3:34pm- More rock going down on roadway at spring where all the potholes were at. 

4:30pm- I will now be offsite. 