8:50am- Entrance for access road 3 is getting built today.
9:35am- More roadway is dug out for 0-6” rock at Mr. Heads Property on access road 1.
10:10am- Access road 3 entrance now rocked in place.
11:45am- More clearing of brush along access road 1 on Rittenhouse is getting done per property owners request and agreement with Flat Creek.
12:10pm- Another load of 0-6” rock going down at Mr. Heads property crossing.
12:30pm- crossing completed.
12:40pm- Staging area back on Rittenhouse property is now covered with 0-6” rock along with rest of roadway into bottom field.
2:40pm- A small diameter drain line will now be installed across access road 1 at the spring area to help with keeping the water out of the roadway.
2:50pm- Pipe is now across access road 1 at the spring.
3:34pm- More rock going down on roadway at spring where all the potholes were at.
4:30pm- I will now be offsite.