Turkey Creek Ph1 - Flat Creek (Line Work)


Very little clearing is now left here at power substation area between MH A35 & A36.  
Looking down line from gate. 

Looking up line towards MH A36 from gate. 

8:35am- First brush pile and a lit this AM. 

9:20am- second pile now lit as the excavator clears to roadway. 

11:10am- Survey crew out staking centerline with cuts for blasting late this week if not early next week. 

12:30pm- Excavator moves to bottom below substation to finish clearing now where TCE was staked out this AM. Survey crew also moving to stake TCE between tracks and Rittenhouse access road 3 creek crossing.  

2:00pm- more trees to come out on the right side of picture at this time. 

3:30pm- brush pile is now huge from clearing of TCE in the bottom area. Cedar trees in lower right is all that’s left to be removed. Another pile of brush will have to be started. 

4:40pm- the two fires lit this morning are getting stoked back up. 



5:20pm- crew is calling it a day. 