Monday, December 30, 2019

Turkey Creek Ph 1 - Flat Creek (Line Work)


Flat Creek foreman is not onsite today due to being sick. I have unlocked gates this AM for crews to work. Drilling & Blasting will continue from substation out to roadway or as much as they can get done today. 

8:05am- Bob will continue to clear TCE today as he heads towards tunnel. 

9:30am- Drilling will only be done for the first 100-150 feet today. Blasting will then occur. 

11:25am- Holes are now being loaded for blasting. 

12:40am- Blasting went off ok. Crew has mentioned that they may go ahead and drill more today. 



I’ll now be off offsite due to becoming ill. 