Turkey Creek Ph 1 - Flat Creek (Line Work)


6:56am- Hammer is repaired and rock breaking will continue today onto stubout at A1. 

8:18am- flushing crew is currently doing some fencing repairs from MH A3 - A6 area. 

9:56am- crew will get pump set up here at MH A14 to continue with flushing the line. 

11:04am- balled being pulled now from A13 for flushing. 

12:57pm- ball at MH A12 has been pulled. A few buckets of gravel were removed prior to flushing. 

1:28pm- pump is now getting set up at MH A12. 

3:07pm- ball pulled at A11 and now getting set up in A10. More gravel was removed from here first. 

4:06pm- ball at MH A10 is pulled now. 
This is the last one for today. 

4:38pm- still breaking rock. Closer now, but still several feet to go. 