Wednesday, December 16, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:50am- crew working on backfill this morning to get atop pipe and set MH A2. Final tie in should be completed by emd of day. 

8:42am- mandrel now completed down to MH A28 from A31. 

8:53am- MH A29 has seepage. 

9:36am- Ace Pipe now at MH A26 to continue with camera and Mandreling. 

10:20am- MH A2 base now set. 

10:34am- very slight sag in bore between MH A27-28 on 12” line. 

11:10am- mandreled now to MH A27. 

1:15pm- MH A2 is now set and pipes are tied in all the way to Liftstaion. 

2:03pm- mandrel now pulled from E1 to A26. 
3:04pm- Trench seal between RR01 and MH A2 now placed. 

3:11pm- Wrapping and strapping MH A2 is underway. 

3:42pm- mandrel now at MH A25 pulled from A26. 
4:41pm- another slight sag in pipe, this time on 27” run between A23-24. 



5:18pm- Mandrel now pulled to A23 from A24. Crew will pack up and call it a day. 