Tuesday, December 22, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:00am- Ace Pipe will be back again today to finish up with video and Mandrel work. Flatcreek crew will begin line testing again today at MH A2 and finish with vacuum testing from A6 downstream. 
7:36am- lids to be bolted down first, then vacuum testing. 

8:40am- Ace Pipe is back to finish now at WWTF MH A2 -A3. 

9:46am- all 27” pipe is now videotaped. Mandrel will be pulled from A3-A1 on 1-16-2021. Crew will now proceed to A36-A37 for their last 12” segment of pipe. 

11:02am- camera crew now at MH A37 -A36. 

11:39am- mandrel is now pulled from A37- A36 manhole. 

12:07pm- MH A6 passes vacuum test. 

12:58pm- MH A5 passes vacuum test. 

1:36pm- MH A4 passes vacuum test. 

2:19pm- MH A3 passes vacuum test. 

3:33pm- air test now started on line from MH A2-A3. 

5:03pm- line passes air test from A2 -A3 manholes. 