Tuesday, December 15, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:50am- gravel has been delivered to WWTF for pipe laying today. Crew will be working on getting Bore tied to MH A2.

8:50am- Ace Pipe has now arrived back at MH A33 to attempt to camera and Mandrel lines. 

10:04am- pipe now getting laid from bore tie in headed to MH A2. 

10:11am- camera has now reached MH A36 from A33 location. Crew will get mandrel adjusted and begin pull back. 

10:37am- 2nd pipe being placed now. 

11:46am- 3rd joint placed. 

12:23pm- 4th joint. 

1:00pm- Ace Pipe has finally got the Mandrel adjusted and pulling begins at MH A36. 



2:30pm- After pulling mandrel for a ways without a tag line attached, crew had to push mandrel with camera back to MH A36 to secure a tag line. The mandrel has now been pulled from MH A36 to MH A35. 



2:50pm- MH A35-A34 mandrel pull. 

3:03pm- MH A34-33 mandrel pull. 
4:10pm- mandrel now at A32 from A33 respectively. 



4:20pm- mandrel now at A31 from A33. 

4:50pm- Camera crew will film onto MH A28 from here at A31 yet to tonight. I will meet them back here in the morning for Mandreling. 