Monday, December 28, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


Crew will finish testing of lines today on the 12” from MH A37-36,& 30-28. 

8:45am- crew is currently working to find sewer line from Liftstaion across the roadway due to it being located on MH A37 side per HOA maintenance personnel. (?)

11:00am- crew now preparing to test line from A28-A29. 

11:15am- Manhole A28 passes vacuum test. 

11:45am- line passes air test from A28-A29. 11 minutes and 20sec. 

12:03pm- MH A29 passes vacuum test. 

12:28pm- line passes air test from A29-A30. 

12:47pm- MH A30 passes vacuum test. 

1:23pm-line on test from MH A37-A36. 500.14’@ 28.5 minutes. 

1:57pm- line passes test from MH A37-A36. 

3:18pm- MH A37 passes vacuum test. All testing now completed on Ph 1. 

3:45pm- The last section of roadway is getting gravel at Mr. Heads property now. 

4:40pm- crew will begin with grouting manholes per punch list here at A30 to round out the day. 