6:56am- hole will be pumped out first thing this morning so rock breaking can continue.
7:20am- flushing crew will fill the line here at A24 again today for the last flush at MH A19 before moving pump to A19 location for filling and flushing next section of line.
8:40am- crew thawing out pump due to it not being drained from yesterday.
8:45am- finally pumping water to fill line to MH A19.
11:13am- ball is pulled at MH A19. Crew will move pump now to MH A18.
12:38pm- now pumping water into MH A18 to begin flushing from here downstream.
1:00pm- ball is getting pulled ar A17 as line is now full.
2:14pm- ball was pulled A16 and will now be placed at A15.
3:42pm- MH A16 running over so crew will now pull ball at A15.
3:46pm- line appears to be flushing clean. Crew will move pump now from A18 to A14 location to be ready for tomorrow.
4:10pm- Rittenhouse property at MH A6- A3. Dirt work getting down as topsoil is spread back out.
4:35pm- so, hammer is down currently and crew hopes to have it back operational by morning. Still a-lot of rock to break to get to stubout from A1. MH A2 area is finished.
Ending the day on a good not now; the water coming into bore pit is now clear at this time.