7:00am- crew worked last Friday installing Rip Rap at RR01 and MH A2 area.
Ground is rough graded out at MH A1 and A2.more cleanup to occur here.
7:42am- another drainage pipe is placed at “spring” area on access 1 per owners request.
9:30am- rock from pipe yard is going on access 1 roadway now.
11:20am- Ace pipe is now back onsite at MH A11 to continue with videoing and Mandreling the lines.
11:54am- Mandrel now at A11 from A12.
12:46pm- Mandrel now at MH A10 from A11.
1:00pm- Mandrel at A9 from A10.
2:05pm- mandrel now at MH A8 from A9.
2:20pm- mandrel now at MH A7 from A8.
2:27pm- a slight sag in this run from A7-A6 from 37’ in at A7 to 71’ in.
3:20pm- Mandrel at MH A6 now. Crew has moved to this side now to continue.
4:20pm- Mandrel now at MH A5 from A6.
5:46pm- Mandrel not at MH A4 from A5.
6:06pm- Mandrel now at MH A3 from A4.