Turkey Creek Ph 1 - Flat Creek (Line Work)


6:58am- more backfill and cleanup to occur here at MH A2 area. 



7:56am- Ace Pipe will pick back up the camera and mandrel work starting here at MH A22 this morning. 

9:15am- line from A23 to A22 now mandreled. 

10:08am- Mandrel not at MH A21 from A22. 

10:19am- Now mandreled to A20. 
11:22am- welders are onsite today to weld gates n place. 

11:28am- Mandrel now at MH A19 from A20. 

11:47am- Mandrel now at MH A18 from A19. 
11:50am- MH A1 getting wrapped and strapped. 

12:39pm- mandrel now at A17 from A18. 

1:12pm- Mow at MH A16 from A17. 
1:42pm- another slight sag in pipe between A15-16. 

2:04pm- Mandrel now at MH A15 from A16. 

2:35pm- Mandrel now at A14 from A15. 

2:40pm- MH A1 is finished and A2 has next section done respectively. 



3:27pm- Mandrel now at A13 from A14. 

3:38pm- mandrel now at A12 from A13. Crew calling it a day here. 

4:12pm- crew still backfilling around manholes. Lid will be placed on MH A2 and wrapping and strapping should be finished up tonight. 

I will now be headed offsite. 