12:10pm- crew has now made it to stubout on MH A1.
12:40pm- bottom land along MH A6 - A3 is cleaning up nicely!
1:34pm- flushing crew back flushing lines and have ball in at MH A8 now. Also crew is winding up electric fence and getting it out of the way.
3:11pm- crew looking to see whats the best way to get MH A2 tied in.
4:00pm- gravel is now placed over stubout at A1 incase of ditch collapse that may occur with rains predicted for tomorrow.
4:56pm- crew calls it a day. Work to resume on Monday. Chris will be onsite tomorrow to move some dirt around at MH A1-A2 area.