Tuesday, December 29, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


8:20am- crew had a late start today due to early am rain. More cleanup in area of MH A31-28. And grouting continues at MH A30. 



9:30am- MH A30 now grouted. 

10:47am-  MH A29 now grouted. 

Cleanup still occurring also. 

11:41am- MH A28 now grouted. This finishes all 12” manholes. 

12:29pm- grouting to resume here at MH A10 here shortly. 

2:00pm- crew has i stalled a ball at MH A11 to stop water and are now in MH A10 grouting. 

2:50pm- MH A10 now grouted. 

4:24pm- MH A9 now grouted. 