Friday, January 8, 2021

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:06am- gate installs will begin today on Laytons upper and middle gates. 

9:07am- old gate and fence now removed and new post holes going in at upper gate.

10:14am- more manhole lids are getting bolted down today throughout the project. 

12:36pm- hammer has now been brought to break rock for post at middle gate here on Laytons. 
Concrete to arrive at 1pm for posts. 

3:22pm- both gates (upper and middle) posts are concreted in place now respectively. 



4:37pm- stumps and brush at top of “Head” roadway 
are getting burned today. This will round out the day. 