7:06am- gate installs will begin today on Laytons upper and middle gates.
9:07am- old gate and fence now removed and new post holes going in at upper gate.
10:14am- more manhole lids are getting bolted down today throughout the project.
12:36pm- hammer has now been brought to break rock for post at middle gate here on Laytons.
Concrete to arrive at 1pm for posts.
3:22pm- both gates (upper and middle) posts are concreted in place now respectively.
4:37pm- stumps and brush at top of “Head” roadway
are getting burned today. This will round out the day.