Monday, January 4, 2021

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:39am- crew is back to grouting manholes this morning starting at A8. 

9:45am- MH A8 near done now. 

10:23am- MH A8 now completed. 

11:00am- MH A7 now done. Pipes has already been grouted around. Flowline into pipe is all that was done. 
About an 18” drop. 

11:40am- castings are now getting bolted down and lids as well. 

1:40pm- another manhole casting bolted down here at A9. 

2:48pm- more lids getting bolted down. 

3:32pm- last manhole frame to be bolted now at MH A19 for today. Crew will continue to work on punch list items. More castings and lids to be bolted tomorrow from A6-A1. 