6:55am- crew to bolt down castings and lids from A6-A3, then more grouting.
7:25am- crew stoking fire to ensure complete burning of pile from yesterday.
8:10am- MH A4 & A5 castings and lids are now bolted down respectively.
8:26am- MH A3 now completed.
9:32am- crew now at MH A2 to do grouting and bolt downs.
11:32am- MHA 2 now grouted.
1:00pm- 12” drop now in MH A2, strapping of drop to happen when straps arrive in the next few days.
2:08pm- MH A1 & A2 are now bolted down. Flowline in A1 to be done by RL Persons crew.
3:07pm- MH A6 casting bolted down, ball pulled and lid getting placed with bolts now.
3:53pm- now at MH A26 for 12” drop work.
5:01pm- 12” drop in except for strapping here at MH A26.
5:08pm- ball going in at E1 on stub out side to eliminate water entry into 27” line.