Wednesday, January 6, 2021

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:55am- crew to bolt down castings and lids from A6-A3, then more grouting. 
7:25am- crew stoking fire to ensure complete burning of pile from yesterday. 

8:10am- MH A4 & A5 castings and lids are now bolted down respectively. 



8:26am- MH A3 now completed. 

9:32am- crew now at MH A2 to do grouting  and bolt downs. 

11:32am- MHA 2 now grouted. 

1:00pm- 12” drop now in MH A2, strapping of drop to happen when straps arrive in the next few days. 

2:08pm- MH A1 & A2 are now bolted down. Flowline in A1 to be done by RL Persons crew. 


3:07pm- MH A6 casting bolted down, ball pulled and lid getting placed with bolts now. 

3:53pm- now at MH A26 for 12” drop work. 

5:01pm- 12” drop in except for strapping here at MH A26. 

5:08pm- ball going in at E1 on stub out side to eliminate water entry into 27” line. 