Turkey Creek Ph 1 - Flat Creek (Line Work)


6:47am- Crews will be working on punch list again today, finishing burning brush and stumps at Access 1 entrance and fixing fence at gates on Layton. 

7:42am- fence is now going back up and will be attached to the new gate posts set last Friday here on Layton. 

9:16am- Fence completed at middle gate on Laytons access road 3. Gates to be welded on tomorrow morning. 

10:57am- top gate fencing now built onto new posts. 