Monday, January 11, 2021

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:47am- Crews will be working on punch list again today, finishing burning brush and stumps at Access 1 entrance and fixing fence at gates on Layton. 

7:42am- fence is now going back up and will be attached to the new gate posts set last Friday here on Layton. 

9:16am- Fence completed at middle gate on Laytons access road 3. Gates to be welded on tomorrow morning. 

10:57am- top gate fencing now built onto new posts. 






Friday, January 8, 2021

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:06am- gate installs will begin today on Laytons upper and middle gates. 

9:07am- old gate and fence now removed and new post holes going in at upper gate.

10:14am- more manhole lids are getting bolted down today throughout the project. 

12:36pm- hammer has now been brought to break rock for post at middle gate here on Laytons. 
Concrete to arrive at 1pm for posts. 

3:22pm- both gates (upper and middle) posts are concreted in place now respectively. 



4:37pm- stumps and brush at top of “Head” roadway 
are getting burned today. This will round out the day. 









Thursday, January 7, 2021

Wednesday, January 6, 2021

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:55am- crew to bolt down castings and lids from A6-A3, then more grouting. 
7:25am- crew stoking fire to ensure complete burning of pile from yesterday. 

8:10am- MH A4 & A5 castings and lids are now bolted down respectively. 



8:26am- MH A3 now completed. 

9:32am- crew now at MH A2 to do grouting  and bolt downs. 

11:32am- MHA 2 now grouted. 

1:00pm- 12” drop now in MH A2, strapping of drop to happen when straps arrive in the next few days. 

2:08pm- MH A1 & A2 are now bolted down. Flowline in A1 to be done by RL Persons crew. 


3:07pm- MH A6 casting bolted down, ball pulled and lid getting placed with bolts now. 

3:53pm- now at MH A26 for 12” drop work. 

5:01pm- 12” drop in except for strapping here at MH A26. 

5:08pm- ball going in at E1 on stub out side to eliminate water entry into 27” line. 















Tuesday, January 5, 2021

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:25am- cold start to the day as crew sets ball at MH A6 upstream to seal water out so grouting can continue today on downstream. 

8:11am- more cleanup in order to burn a pile of brush this morning. 

10:06am- after failed attempt at burning, crew is back to grouting from MH A6 on downstream. 

10:45am- MH A6 now grouted. 

12:26pm- MH A5 now grouted. 

1:57pm- grouting on MH A4 now as second attempt on lighting fire begins. 

2:54pm- MH A4 is now grouted. 

5::00pm- MH A3 grouting is nearly complete for rounding out the day. 











Monday, January 4, 2021

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:39am- crew is back to grouting manholes this morning starting at A8. 

9:45am- MH A8 near done now. 

10:23am- MH A8 now completed. 

11:00am- MH A7 now done. Pipes has already been grouted around. Flowline into pipe is all that was done. 
About an 18” drop. 

11:40am- castings are now getting bolted down and lids as well. 

1:40pm- another manhole casting bolted down here at A9. 

2:48pm- more lids getting bolted down. 

3:32pm- last manhole frame to be bolted now at MH A19 for today. Crew will continue to work on punch list items. More castings and lids to be bolted tomorrow from A6-A1.